At CNMC, we don't allow any server on our network until it has been certified in our test environment. Each server is inspected and assembled by our technicians who are the best in the business. By going this extra mile, we afford our clients some extra peace of mind and some security in knowing that their data and Internet business are on a proven robust platform. Industry statistics have shown that most common failures occur in the first 48-72 hours of server usage. Our burn-in period is 72 hours ensuring that all of the most common failures will occur and be corrected prior to putting a server in to production.
Please see the following table to understand our rigorous rollout schedule and sequence.
Day(s) |
Action Performed |
|
|---|---|---|
| 1 | Server inspected and assembled to client specifications – spare parts catalogued and stored with client file |
|
| 2 | Windows 2003 Server installed, patched to current |
|
| 2 | Vision Backup, Acronis System Imaging, Trend Micro Interscan Viruswall installed |
|
| 2-4 | Burn-in |
|
| 5 | CNMC test environment sign off |
|
| 5 | Racked in CNMC data center |
|
| 5 | IP and Firewall configuration |
|
| 6 | Any special client configuration requests – if applicable |
|
| 6-7 | Stress and Load testing |
|
| 7 | Network Penetration Testing |
|
| 8 | Server is production ready |